From Local 3 News: The developers of Project River, which includes a proposed data center in Bradley County, have agreed to the City of Cleveland’s development requirements, which they say “mandate significant community benefits.” Requirements address many community concerns, including noise and light pollution, visibility from connecting roads, and environmental impacts.
Project River is a proposed $11.3 billion industrial campus on 850 acres in Bradley County. The Wright family says the whole campus will be self-powered.
The City of Cleveland will finalize its draft of the Planned Unit of Development 77 (PUD 77) on Friday, September 18. However, a proposed draft is already available, and developers have agreed to its guidelines.
Developers told Local 3 News they would present the project to the City Council and Planning Commission on September 21.
A vote is not expected until at least October. If passed, it will act as law.
Overall project requirements:
Developers must provide land and funding for a new emergency response station for fire, EMS, and police on Lower River Road. The Wright family says they must also improve infrastructure in that area, near Exit 33, including access points, traffic signals, and more.
Project River developers will also have to negotiate a community benefit agreement to support schools in the City of Cleveland and Bradley County. The agreement must also provide support for projects and infrastructure in the City of Cleveland, Bradley County and the City of Charleston.
The project also restricts log trucks from using any city streets or county roads, and a data center cannot be viewable from any public roads or adjoining properties.
If a data center is developed, it will be subject to additional requirements related to screening, storm water management, lighting, noise, heat and emissions, according to the Wright family.
Data center operators will be required to submit studies and mitigation plans, and the City will be able to test for and enforce compliance during construction.
Other requirements include:
The Bradley County community has been vocal about opposition to Project River. Hundreds of people showed up at Monday’s Cleveland City Council meeting, and a petition to reject the project has more than 4,000 signatures.
Wright Brothers Construction previously held a public meeting to answer questions about the project. However, attendees had to submit questions online, some of which were answered during the meeting. There was no opportunity for public input during the meeting, which resulted in chants and yelling from the audience.
The City of Cleveland says the Planning Commission will discuss Project River on Monday, September 21 at 6:00pm, but there will be no official action or vote.
Read the City of Cleveland PUD release HERE.
Project River is a proposed $11.3 billion industrial campus on 850 acres in Bradley County. The Wright family says the whole campus will be self-powered.
The City of Cleveland will finalize its draft of the Planned Unit of Development 77 (PUD 77) on Friday, September 18. However, a proposed draft is already available, and developers have agreed to its guidelines.
Developers told Local 3 News they would present the project to the City Council and Planning Commission on September 21.
A vote is not expected until at least October. If passed, it will act as law.
Overall project requirements:
- Data Center – 500 feet from property line
- Power Plant River Front – 200 feet from property line
- Power Plant Non-River Front – 50 feet from property line
- Exceptions – Barge Port, Stormwater Facilities
- Developers must provide land and funding for a new emergency response station for fire, EMS, and police on Lower River Road. The Wright family says they must also improve infrastructure in that area, near Exit 33, including access points, traffic signals, and more.
Developers must provide land and funding for a new emergency response station for fire, EMS, and police on Lower River Road. The Wright family says they must also improve infrastructure in that area, near Exit 33, including access points, traffic signals, and more.
Project River developers will also have to negotiate a community benefit agreement to support schools in the City of Cleveland and Bradley County. The agreement must also provide support for projects and infrastructure in the City of Cleveland, Bradley County and the City of Charleston.
The project also restricts log trucks from using any city streets or county roads, and a data center cannot be viewable from any public roads or adjoining properties.
If a data center is developed, it will be subject to additional requirements related to screening, storm water management, lighting, noise, heat and emissions, according to the Wright family.
Data center operators will be required to submit studies and mitigation plans, and the City will be able to test for and enforce compliance during construction.
Other requirements include:
- Green Space: 20% of the land must remain green space.
- Max Building Height: Max building height will be 85 feet, and average height will be 70 feet.
- Grading: Minimize grading and site disturbance to maximize retention of native vegetation, topsoil, and landforms. All cleared areas are to be revegetated with native vegetation.
- Environmental: An environmental study must be conducted before receiving a data center permit.
- Noise: Limiting noise to a maximum of 60 decibels at the property line. The City must approve a noise mitigation plan, and noise will be continuously monitored at the property line.
- Lighting: A lighting plan will be approved by the City during the site plan review process, with an annual review for the first five years.
- Cooling: Requires a closed-loop cooling system.
- Dust Control: Project River must comply with National Fire Protection Association (NFPA) standards.
- Conveyor System: A conveyor system must be fully enclosed to reduce wind-borne erosion.
- Biomass Facility Emissions: The project must use Best Available Control Technology to capture and minimize combustion emissions. The facility must feature a Continuous Emissions Monitoring System (CEMS) to track output.
- Power: 75% of all direct power used must be generated on site. It requires a yearly sustainability report detailing power use to the City.
- Water: 90% of all process water used (excluding initial system priming) shall be generated on site. It requires a yearly sustainability report detailing water use to the City.
- Hiwassee River: It may not directly connect the utility to the Hiwassee River.
The Bradley County community has been vocal about opposition to Project River. Hundreds of people showed up at Monday’s Cleveland City Council meeting, and a petition to reject the project has more than 4,000 signatures.
Wright Brothers Construction previously held a public meeting to answer questions about the project. However, attendees had to submit questions online, some of which were answered during the meeting. There was no opportunity for public input during the meeting, which resulted in chants and yelling from the audience.
Read the City of Cleveland PUD release HERE.
Posted in Local News
Recent
Lee's School of Music to present annual Faculty Gala Monday
September 16th, 2026
City of Graysville suspends its city recorder
September 16th, 2026
Candy’s Creek Cherokee Elementary surprise custodian with a new car
September 16th, 2026
‘Project River’ developers accept City of Cleveland’s requirements on potential data center
September 16th, 2026
Cleveland State accepting nominations for 2027 Community First Awards
September 15th, 2026
Archive
2026
January
Cleveland man among two arrested after biker gang stabbing in TazewellTennessee sees fewer deadly crashes, Georgia sees more holiday traffic deaths2 women, 2 children found dead in Waverly home during welfare checkFormer TN Rep. Robin Smith seeks probation in federal mail fraud caseBradley County Commission meeting recapTDOT temporarily closing lanes along I-75 in Bradley, McMinn Counties"She admitted her mistakes": Former TN Rep. Robin Smith's pardon attorney fighting for presidential probationHundreds of DUI arrests in TN ended with no drugs or alcohol detected, TBI reportsBradley Co. Schools to begin training on weapons detection systems, aimed at enhancing campus safetyCleveland City Schools announces leadership transitions after 2026 school yearMulti-vehicle crash on I-75 South Tuesday afternoonAthens man receives one of the longest sentences in TN history in child sex abuse caseJenkins Deli to close after nearly 50 years in businessPolk County receives $500,000 Tennessee Historic Development Grant for courthouseGun found in student's car at McMinn Co. High; juvenile chargedCleveland Mayor Kevin Brooks delivers State of the City addressCleveland State announces Community First AwardsMotorcyclist killed in crash on Ooltewah Georgetown Rd. Sunday morningLake Winnie gets new operator; set to begin in 2026 seasonTennessee’s unemployment rate decreases in NovemberBradley County Commission meeting recapCleveland City Council meeting recapCleveland State presidential search advisory committee appointed; public forum set for WednesdaySmall plane crashes in Polk County TuesdayMcMinn Co. High School placed on temporary lockdown following "concerning comment" made by studentCleveland City School Board meeting recapHuman remains found in wooded area near EtowahTennessee Sandhill Crane Festival to celebrate 35th anniversary January 17-18Tennessee residents may soon vote to ban state property tax foreverGov. Lee proclaims January 19 as "Dolly Parton Day"United Airlines temporarily offering direct flights from Chattanooga to DenverBarn blaze leaves 9 animals dead in Bradley County ThursdayBradley County Mayor Gary Davis delivers annual State of the County addressNo injuries reported after crash on Paul Huff Parkway SaturdayPetroleum pipeline maintenance under Mouse Creek Road to cause delaysCharleston home a complete loss after fire Saturday afternoonTwo vehicle crash on I-75 S causes temporary road closure SundayBradley Medical Center and Erlanger to partner to expand pediatric emergency servicesOoltewah man arrested after auto burglary spree, HCSO saysDecember Tennessee revenues exceed budgeted amounts by $82.7 millionTennessee lawmakers push to expand school voucher program as demand surges past 50,000Bradley County Commission meeting recapCleveland man arrested after making threats to judge, criminal justice officialsYour to-do list ahead of the winter storm heading toward the TN ValleyOfficials urge residents to prepare now for unpredictable winter weather in TN ValleySPCA of Bradley County temporarily closing due to winter weatherBradley County EMS to begin carrying CYANOKITTennessee and Georgia declare state of emergenciesCleveland City Schools names Mike Chai as new Director of Student ServicesSheriff Steve Lawson discusses updates and future needs of BCSO ThursdayMan wanted for attempted murder in Athens stabbing considered dangerousCleveland City Schools and CPD launch BusPatrol ProgramBradley County government offices closed MondayTDOT crews help drivers across the stateMcMinn Co. deputy praised for heroic response to deadly crash after pursuit of stolen vehicleCleveland City Council meeting recapCleveland's Long Range Transportation Plan draft focuses on congestion, safetyApartment catches fire Sunday in ClevelandVolunteers needed for Barbara's Market in ClevelandTBI activates hotline to support welfare checks after winter stormBlood Assurance offers $40 eGift Cards to donorsLee University, City of Cleveland partner to celebrate Sousa’s Musical LegacyFormer Hamilton Co. teacher sentenced to 60 years following conviction of child sexual abuseCleveland firefighters quickly extinguish basement fire Wednesday nightKnox County man charged with first-degree murder after body found in Ten MileBCSO to host blood drive with Blood Assurance on Feb. 9Cleveland PD Chief Mark Gibson delivers 2026 New Year's MessageUnemployment rates below 5% in nearly every Tennessee countyGov. Lee requests expedited disaster declaration for 23 counties
February
Cleveland community mourns death of Bradley Central student athleteBradley County government offices closed MondayCleveland firm laying off 100 employees starting April 1'Infrastructure challenges' blamed for failing health inspection score at Benton ElementaryGov. Lee delivers 2026 State of the State Address: “Tennessee: The Original Frontier”Tennessee lawmakers, DA look to ensure death penalty as option for child rape"It's disappointing": Cigna Healthcare says CommonSpirit sought price increases, rejected current contract amid failed negotiationBCSO to host blood drive with Blood Assurance on Feb. 9TDCI and Tennessee AG issue joint statement about Winter Storm FernCleveland City Schools AI bus cameras already catch drivers illegally passingTennessee reaches nearly $18M settlement with drug companies over alleged price gougingHow many arrestees were turned over to ICE? New Tennessee report breaks it down by countyVolkswagen, UAW reach contract agreementBradley County Fire and Rescue responded to 2 structure fires Wednesday morningUPDATE: Manhunt continues for suspect in attempted murder after known 'associate' chased through Bradley, Polk Counties8 students charged after brawl at Cleveland High SchoolCleveland man arrested after armed domestic dispute, standoffEx-NFL player charged with girlfriend's murder; victim identified2026 Winter Job Fair to take place Feb. 13UPDATE: Missing Athens, TN woman found safeBradley County Commission meeting recapCleveland City Council meeting recapBradley County School Board meeting recapUTC students react to new safety app after 2025 false shooter scareFormer Tennessee private school principal has child sex charges reduced, learns sentenceTellico Plains police officer indicted in statutory rape investigation, TBI saysNew Tennessee bill further protects places of worshipCHS receives $10,000 grant to enhance Tango Flight ProgramBradley County Sheriff's Office warns of local scamAllegiant Air begins nonstop route from CHA to Fort LauderdaleLee University names Johnson Director of Community and Church Relations